Case Study : Roof Repair & Replacement

Loss Event: Hurricane Damage

Repair and replacement of roof

Scope of project:

  • 30% damage reported on the roof and large portion of sub-structure was destroyed
  • US Roofing Systems purchased over 65 camper trailers and leased enough land to set them all up for sustainable housing for the crew
  • US Roofing Systems supplied a full-time chef to prepare 400 meals per day for the crew
  • Full replacement of fasteners
  • Installation of a FiveV Crimp style steel roof
  • Installation of FT synthetics Platinum HT-SA high temp self-adhering roofing underlayment
  • Upon completion new roof had double the anchor points of original roof
  • Completion time: 3 months.